Planning optimization use casesThe planning clock. What is planned at night has to work in the morning.
Every operation has a moment when the plan must be right. For winter road service it is 06:00, for home care 06:30, for machining the start of the shift. Here all use cases are sorted by that moment. Each one plays in your browser: the plan in time-lapse, with KPIs and the comparison to the usual way of planning.
How to read the clock
Every dot is a use case. It sits at the time its plan has to be ready. Orange marks the morning. Because most plans are due then, the morning takes more room on the dial; dots that would sit too close move apart a little, and an orange mark on the ring shows their exact time. The squares on the outer ring plan over days or months. A click opens the case.
Night 18:00–06:00
Motorway renewal closures and crews
A 12 km motorway stretch renewed in 16 work zones. Night closures or weekend full closures, 2 milling machines, 2 paver trains and 1 to 5 asphalt crews compared.
Train depot night stabling
15 train sets arrive in the evening and leave in the morning. Sidings are last in, first out, so the wrong siding blocks a departure.
Night bus ride pooling
Bookings from the last trains, the village pub and between villages. Three minibuses pool the rides home on real roads.
Industrial bakery night production
About 120 dough batches, seven kneaders, four make-up lines, eleven ovens and 15 tours that leave between 01:45 and 05:30. Dough cannot wait, so the order of the doughs decides the night.
E-truck charging hub motorway
Long-haul trucks charge in the 45-minute driver break, regional trucks top up between tours. Megawatt and CCS bays share a limited grid connection.
Rail depot night maintenance
Wash plant, inspection pits, drop pit and wheel lathe; one shunting crew moves the trains through the switch ladder.
E-bus depot overnight charging
24 e-buses, 10 chargers and a 900 kW grid connection. Every bus is ready for its morning block, charged at night prices.
Assembly line mixed-model sequencing
400 utility vehicles in many variants, 32 stations at a takt of 72 seconds, a paint shop that wants long colour blocks and suppliers who deliver just in sequence.
Winter road service snowfall overnight
Snow starts at 03:30. Three spreader trucks plough and salt 61 km of real roads around Windhagen, the main roads by 06:00.
Aircraft maintenance hangar planning
Four bays, two aircraft in a heavy check and three overnight checks every night. Every aircraft has to be released before its next flight.
Morning 06:00–09:00
Airport stand allocation
46 flights in the morning bank, 10 contact and 21 remote stands, three pushback tugs and six apron buses.
Staff scheduling by demand warehouse
54 people, four areas, one day. Shifts start on the quarter hour and follow the forecast workload in goods-in, picking, packing and dispatch.
Store delivery e-trucks from the DC
Ambient, chilled and frozen orders for 28 stores on diesel and electric trucks. Loading order, store access, range and charging planned together.
Home care tours and continuity of care
A home care service with 42 clients and 14 carers. One week of tours with morning and evening peaks, split shifts, six pool cars and few different carers per client.
Operating rooms weekly scheduling
Eight operating rooms, six specialties, a waiting list of 146 patients, a recovery room and ICU beds. The week is planned ahead and re-planned when emergencies arrive.
Bus vehicle and crew scheduling one school day
One school day of a regional bus network with five lines. Every trip gets a bus and every piece of a bus’s day a driver, so the timetable runs with few buses, short empty runs and few paid hours within the driving and break rules.
Parcel hub dock scheduling
Overnight trucks, 12 doors, a sorter for 6,000 parcels per hour and 78 van bays. The morning delivery wave has to leave on time.
Field service routing
Eight technicians, 29 home installations, arrival windows and skills, planned on the real roads around Windhagen.
Call centre flexible staff scheduling
34 agents and a flex pool on four queues, 20 desks and home office, calls per quarter hour. The staffing follows the forecast, and the plan reacts to an outage and sick calls.
Ready-mix concrete one day of pours
16 truck mixers bring 786 m³ from two plants to 12 construction sites. Every pour should run without a break, and the concrete must be placed within 90 minutes.
Parcel delivery districts with core and flex zones
Six drivers keep the streets they know, and on a day with uneven volume a neighbour takes over a few border cells. Two levels: districts from the history, then the routes of the day.
Parcel delivery deliveries and pickups
Six vans, 314 deliveries and 64 pickups in one day. Every stop in its window and no van over capacity at any point of the tour.
Day 09:00–18:00
Production scheduling machining
CNC mills, lathes, welding and assembly; component orders feed assembly, AGVs move the material, workers in shifts.
Production scheduling sheet metal
Laser cutting, bending, robot welding and a powder coating line that runs in colour batches.
Shift rostering 3-shift production
A month of early, late and night shifts with skills, contracts, vacation, rest rules and wishes. Every shift is covered and the work is shared fairly.
Energy-aware production foundry
Induction furnaces, heat treatment, e-trucks, PV and a battery planned together against day-ahead prices and the 15-minute peak.
Warehouse order batching & pick routes
Twelve aisles, 900 articles in chaotic storage, trolleys with several order buckets: shorter walks and faster waves.
Bulky waste collection by appointment
80 households booked a pickup for today, in the morning or in the afternoon. Four trucks collect in the booked windows and unload at the recycling yard when they are full.
Chemical park tanker loading
56 road tankers with booked slots, six loading bays with different product lines, a 25-minute flush per product change and tanks that the plant refills all day.
Intermodal terminal crane scheduling
Two gantry cranes on one runway, three trains and the trucks of the day. Every train has to leave full and on time, and the trucks should not queue.
Agriculture harvest before the rain
Two combines from 10:00, rain from 16:00, two grain carts to the silo. The goal is the most crop value harvested before the weather turns.
Hospital bed allocation
65 beds in three sections and a busy week of planned and emergency admissions. Every patient should get a fitting bed without waiting in the emergency department.
Solar park drone patrols from docks
A solar park of about 100 ha, watched at night by drones based in docks on the site. Which drone flies which sector when, so that no sector stays unseen too long, also at hand-overs and during an alarm.
Days to months Horizon
Warehouse slotting
400 articles, 624 pick slots on three levels: fast movers near goods out, heavy goods low, the ergonomic level for high volume.
Wind farm maintenance in weather windows
28 real turbines, three crews, one mobile crane and a weather front. Services run in calm hours, faults are fixed quickly.
Shelf layout supermarket
Which product goes on which shelf and at which height, and where this week’s non-food offers stand. More sales without slowing down the quick shop.
GEIG car park charging points at a supermarket
From 1 January 2027, existing car parks with more than 20 spaces need one charging point per 10 spaces, or conduit at half of the spaces. The model finds the less expensive way for a store with 90 spaces.
House build project schedule
A detached house with basement, built by 20 trades from 38 candidate companies with their own calendars. 22 deliveries to a small site, crane and scaffold rented by the day.
Bridge build construction schedule
A motorway bridge with 4 spans over a river and a farm road. Two crews, one crawler crane and one deck formwork set, with curing times and a weather calendar.
Pharma field sales visit cycle
Three sales reps, 80 practices and three product lines. Every specialty gets its target visits at the practices’ reception hours, with little driving.
AI compute scheduling 5 data centres
A simulated day with 863 AI jobs on 9,728 GPUs in five data centres. The OptaZEN meta-scheduler plans 24 hours ahead in front of the existing scheduler: which job runs when and where, when data moves and when renting extra GPUs pays off.
Additive manufacturing medical technology
Nine printers for titanium, cobalt chrome, steel, PA12 and resin, 20 post-processing stations, two shifts. Which lot goes on which build plate and printer, and in which order, so surgery dates hold, also after a failed build.
LNG import terminal ships, tank and trucks
A floating LNG terminal, two carriers, 137 trucks and a stormy week. When each carrier berths and how fast it pumps, when each truck loads, so the tank stays inside its band and ships wait little, re-planned after every report.
Tanker inventory routing diesel and gasoline by sea
Four product tankers, two refineries and five tank farms around a fictional sea, three weeks with a cold spell and a storm. Which ship calls where, how much it loads or discharges and how fast it sails, so no tank farm runs dry.
Plant maintenance two weeks of work orders
82 work orders for two weeks, nine own technicians and four external companies. Maintenance uses the gaps of the production plan, and the bottlenecks stop as little as possible.
Plant engineering multi-project planning
Eight customer projects over nine months share engineers, welders, fitters, two assembly bays, one test stand and the commissioning team. One plan for all projects, against contract dates.
School timetable and room plan two buildings
A week’s timetable and room plan for a school with two buildings. Every lesson gets a period and a room, so teachers walk less, wait less between lessons and get the start and end times they asked for.
Recruit training police academy
Months of courses for several recruit classes, with fixed exams, a range off site and speakers who travel in. When a speaker cancels the evening before, the rest of the week is re-planned.
Duty roster care home
A month of early, late and night shifts in three units: enough nurses on every shift, fair weekends, wishes met, and a calm answer when someone calls in sick.
Autonomous trucks with transfer hubs
A vision: autonomous e-trucks drive the motorway, people take over at secure hubs for the first and last mile. What has to be planned for it to work.
Power line inspection drones from vans
About 98 km of real 110 kV and medium-voltage lines, three crews with a van as mobile launch point, one week in March. Which stretch from which launch point on which day, in the weather windows.
Grid build programme distribution grid
About 65 grid measures in one year: scarce crews and transformers, outages that keep the grid supplied, and connection dates that follow from the build plan.