Production scheduling for a sheet metal job shop

In which order do cabinets, brackets and enclosures run through laser, press brake, welding and powder coating — with as few colour changes as possible?

Contract manufacturingEnclosuresMetalworking

Drag to rotate, scroll or pinch to zoom. The schedule below plays the plan; hover a bar for details. Plan computed with a Timefold model.

The planning question

A contract manufacturer cuts, bends, welds and powder-coats cabinets, brackets and enclosures. The powder coating line works in colour batches, so its sequence decides most of the set-up time — but batching too long makes other orders late.

How we plan it

Timefold balances batching against due dates: grouping colours saves set-up, but only as long as no order misses its delivery date.

What the plan shows

KPIOptimized plan
late orders0
tardiness (min)0
set-up (min)530
AGV empty travel (m)1,423

Decisions

  • sequence and start time per machine
  • colour batches on the coating line
  • worker and transport per operation

Constraints

  • operation sequence laser → bending → welding → coating
  • colour change on the coating line costs set-up time
  • curing time before assembly and packing
  • shift times and qualifications

Objective

no late orders, few colour changes, short lead times

Questions

How are colour changes modelled?

As sequence-dependent set-up times on the coating line; the solver trades them off against due dates.

Can rush orders be added?

Yes. A new order is inserted and the open part of the plan is re-optimized, with started operations kept fixed.

More use cases

All use cases

Your planning problem looks different?

Every operation has its own rules. Tell us about yours — we assess feasibility and expected impact in a free initial call.

Book a free call Write to us