Allocation planning

Tanker loading at a chemical park: bays, products and tank levels

Which tanker loads when and at which bay, with the product that is actually in the tank?

Result in this example, compared with “dispatcher rules”: late vs. slot 7 instead of 12, average wait 9 min instead of 15 min, longest wait 48 min instead of 78 min.

ChemicalsTank storageBulk logistics

Drag to rotate, scroll or pinch to zoom. The schedule below plays the plan; hover a bar for details.

The planning question

At the road-tanker loading station of a chemical park, 56 tankers have booked slots for the day. Six bays have lines for different products; changing a bay to another product needs a 25-minute flush. The product tanks are refilled by the plant all day and must never fall below their minimum. A tanker can only load when there is enough product in the tank.

How we plan it

The plan links bays, products and tank levels over time. Sometimes it calls a tanker a few minutes later on purpose, so that its tank has refilled; the tank-level curves in the schedule show why.

The comparison follows dispatcher rules on the same day: a bay keeps its product where it can, calls only tankers whose product is in the tank, and otherwise follows the order of the booked slots. With the rules 12 tankers load more than 30 minutes after their slot and the longest wait is 78 minutes. With the optimized plan it is 7 tankers and 48 minutes, the drivers spend 60 instead of 67 minutes on site on average, and the bays need 11 instead of 12 flushes. Slots, volumes and refill rates are assumptions.

What the plan shows

KPIOptimized planComparison: dispatcher rules
time on site60 min −767 min
average wait9 min −615 min
longest wait48 min −3078 min
bay flushes11 −112
late vs. slot7 −512
bays blocked (tank low)0 min0 min

Decisions

  • bay and order of the tankers on each bay
  • how long a bay holds before it calls the next tanker, so that a tank can refill

Constraints

  • a bay only loads products it has lines for
  • product change on a bay: 25 min flush
  • a tank never falls below its minimum of 15 m³; the plant refills it all day
  • one tanker per bay; check-in, pull-in, papers and seal take their time
  • all tankers loaded by 20:30

Objective

tankers loaded within 30 min of their booked slot, then short waits for the drivers (long waits count more) and few flushes

Questions

Why call a tanker later on purpose?

If its product tank is low, the tanker would wait at the bay until enough product has come in. Calling it a few minutes later lets the tank refill and keeps the bay free for another tanker.

Can production plans be included?

Yes. Tank inflow from production is an input; the same model can also feed back demand to production planning.