Production schedulingCharging optimization
Energy-aware production planning in a foundry
When does each furnace melt, when do heat treatment and the e-trucks charge, and how does the battery run, so that the peak and the energy bill go down?
Result in this example, compared with “today, without battery”: demand charge 735 k€ instead of 998 k€, grid peak 4,900 kW instead of 6,653 kW, energy cost per year 2,816 k€ instead of 3,190 k€.
FoundriesMetalsEnergy-intensive production
Drag to rotate, scroll or pinch to zoom. The schedule below plays the plan; hover a bar for details.
The planning question
An iron foundry over one week in 15-minute slots: two 2.4 MW induction furnaces feed a molding line that pours every 90 minutes, a heat-treatment furnace runs unmanned, six e-trucks charge overnight, 1.5 MWp PV on the roof and a 2 MWh battery. Energy is bought at day-ahead prices, and the highest 15-minute peak sets the demand charge for the whole year.
How we plan it
OptaZEN plans production, flexible loads and the battery in one model: shifting a melt by 15 minutes or a heat-treatment batch into the night often saves more than the battery alone.
What the plan shows
| KPI | Optimized plan | Comparison: today, without battery |
|---|---|---|
| grid peak | 4,900 kW −1,753 | 6,653 kW |
| energy cost per year | 2,816 k€ −374 | 3,190 k€ |
| energy | 2,081 k€ −111 | 2,192 k€ |
| demand charge | 735 k€ −263 | 998 k€ |
Decisions
- furnace and start of every melt before its pour
- start of every heat-treatment batch inside its window
- charger and start of every e-truck
- battery settings: peak target and charge price limit
Constraints
- pour times of the molding line are fixed; large castings need both furnaces
- molten metal held hot at most 2 hours
- melting only while the melt shop is staffed
- grid import below 8 MW
- trucks back in the evening, out at 05:00
Objective
low energy cost and a low 15-minute peak, without touching the casting rhythm
Questions
Does production get slower?
No. Pour times and shifts stay fixed. The model only uses the freedom that already exists: melting a little earlier, heat treatment at night, charging the trucks after the evening peak.
Where do prices and loads come from?
Day-ahead prices from the exchange or the supplier, load profiles from the metering point and the machines; PV from a forecast.
How are the yearly figures calculated?
One sample week is scaled up to a year, and the demand charge comes from the highest 15-minute peak at an assumed 150 € per kW and year. The purchase price of the battery is not included, so the saving is not a payback calculation.
More use cases
Production scheduling machining
CNC mills, lathes, welding and assembly; component orders feed assembly, AGVs move the material, workers in shifts.
Production scheduling sheet metal
Laser cutting, bending, robot welding and a powder coating line that runs in colour batches.
Rail depot night maintenance
Wash plant, inspection pits, drop pit and wheel lathe; one shunting crew moves the trains through the switch ladder.
The first step